🚜 Earthmoving · Loader–Hauler Selection

Equipment Selection Tool

Pick a job's bank volume, material, time and machine, and the tool recommends an excavator/loader + dump-truck fleet: machine and truck counts, bucket passes, production checks, the match factor and the project duration — with a fleet flow diagram.

Free to run · Balance EP

① The job

Load factor LF = 1/(1+swell/100); loose volume LCM = BCM·(1+swell/100). E = 0.83 is a 50-min working hour.

② Available time → required production

Available hours = hours/day × days. Required production Preq = Volume ÷ available hours (BCM/h).

③ Primary machine

Choosing a size pre-fills q, Cm and K — override any of them for your actual machine. Loose volume per pass = q·K (LCM).

④ Hauling truck

Truck travel time

Haul time = dist/loaded-speed; return time = dist/empty-speed (converted to seconds).

🚜 Recommended equipment spread

Loader–hauler selection
Primary machine
Trucks (fleet)
Fleet production
Required Preq
Project duration
Match factor MF

Production summary

QuantityValueUnit

Worked solution

📋 Indicative values — tap to view & adjust
⚠️ Indicative only. These swell %, fill factors K, and cycle times Cm are typical starting points — adjust them to your actual machines & site, and confirm against manufacturer (e.g. Caterpillar Performance Handbook) and course data before using on a real job.

Edit a cell to change the default the form pre-fills. The job efficiency is also editable here.

MaterialSwell %Fill factor K
Machine / size (m³)Cm (s)K hint